SERVICE ACCESS ROAD:
The service road/main access trail construction resumed on Tuesday after sixteen inches of snow and below zero night time temperatures delayed work for 12 days. Wednesday afternoon the heavy equipment left the site and the service road/main access trail construction barricades have been removed. Although at the time of this post the road/trail had not been officially opened.

THE BIVY:
The Bivouac pathways project is expected to resume this Friday, November 28th with work continuing on Saturday and through the first week of December.